REI Aar Ltd

The Club Deal in Aarau involves the development of a residential property within walking distance of the train station.

Aarau, Laurenzenvorstadt

The site currently comprises two buildings: a listed heritage villa and a commercial property. The commercial building is to be demolished, and a new residential building will be developed in its place.

The project is currently in the planning phase. The legally binding building permit is expected in Q3/Q4 2026. The property will then be acquired and construction will commence.

Key Facts

>1.4
Expected equity multiple
3-4
Timeline Years
>15
Expected net IRR Percent
2025
2026
2027
2028
 

June

Signing of purchase agreement

Q3

Development of the construction project

Q1

Building application (no later than nine months after signing the purchase agreement)

Q2

Preparation of implementation project

Q3 - Q4

Obtaining the building permit, clearing conditions and legal validity

Q2

Termination of tenancy, tender and start of construction

Q3

Completion of the construction project Handover of the apartments and buildings